Sprint 2019 July 18 to Aug 7 summary

Below are the tasks we worked on during our last sprint.

Regarding our contributions to Zuul and Nodepool:

  • We got most of the JWT patch chain merged. The GUI part is going to take some time.
  • We added a review documenting the protected REST API in the OpenAPI format. The …
more ...

Sprint 2019 June 27 to July 17 summary

Below are the tasks we worked on during our last sprint.

Regarding our contributions to Zuul and Nodepool:

  • The first few patches in the JWT chain were merged

Regarding Software Factory:

  • We switched managesf to SCL python 3.5
  • We started switching sf-manager to SCL python 3.5
  • We packaged …
more ...


Sprint 2019 May 16 to June 05 summary

Below are the tasks we worked on during our last sprint.

Regarding our contributions to Zuul and Nodepool:

  • We improved the webtrigger interface to support multiple pipeline for different nodeset and detect the default branch.
  • We helped fixes issues in Zuul CI for the containers and tox-remote jobs.
  • We added …
more ...






Sprint 2019 11 Jan to 30 Jan summary

Below are the tasks we worked on during our last sprint.

Regarding our contributions to Zuul and Nodepool:

  • freeze_job: worked on a new zuul-runner command line to be able to run a job locally. This rebased and fix the proposed implementation and added the execute sub-command as well as …
more ...